When a satellite launch slips, four clocks keep running: the rebooking terms in your launch contract, your radio licence, your ITU frequency filing and your funding period. If the delay is on your side, SpaceX for example lets you apply 100 percent of the money already paid to a later rideshare, subject to a rebooking fee of 5 to 10 percent. If the delay is on the provider's side, the SpaceX user's guide says the schedule change is not subject to customer rebooking fees. Your FCC licence, your ITU deadline and your grant end date do not move just because the launch did. This checklist walks through what to check in the first days after a slip, with the rules as published by SpaceX, the FCC, the ITU, ESA and the European Commission.
Why launches slip and how to build buffers is covered in our guide to launch delays. Here the slip has already happened.
Step 1: Find out whose delay it is
Almost everything that follows depends on one question: did the launch move, or did your payload miss it? Launch contracts treat the two cases very differently.
- The provider moved the launch: The SpaceX Rideshare Payload User's Guide (Version 11, August 2026, section 9.6) states that a material failure by SpaceX to meet its responsibilities "may result in changes in the scheduling of the Launch Period or Launch Date; such changes are not subject to any Customer rebooking fees." SpaceX also sets the launch date itself: it will advise the customer of the launch date about 60 days before the start of the launch period, determined "in its sole discretion" (section 9.6.1).
- Your payload is late: Section 9.5 of the same guide says that a material failure by the customer to meet its responsibilities, "including any non-compliance with the Payload ICD, may result in a Customer delay requiring rebooking with applicable fees."
- Licences are late: If an action or omission of the customer forces SpaceX to delay a licence application it is responsible for, or if SpaceX decides that a needed export or other licence is not possible within a reasonable time, SpaceX reserves the right to re-book the customer with applicable rebooking fees, or to terminate the agreement and return all amounts paid, without interest (sections 9.2 and 9.6.8).
NASA describes the same logic for CubeSats flying as secondary payloads. In CubeSat 101 (NASA CubeSat Launch Initiative, October 2017) it writes that only the primary mission or the launch vehicle can move the launch date, and: "If your CubeSat is not delivered in time, the LV will definitely leave without your CubeSat onboard."
Our own advice from these rules: get the reason for the slip in writing from your provider or broker, and ask how the contract classifies it. That classification decides whether you pay a fee.
Step 2: Read the rebooking and termination clauses
SpaceX is one of the few providers that publishes its rebooking terms. On its rideshare page (checked on 7 November 2026) it states under "Contract flexibility": "If your payload is delayed, apply 100% of monies paid toward the cost of rebooking on a future mission, subject to a 5-10% rebooking fee." Other providers and brokers set their own terms in the launch service agreement, so the numbers below are only the SpaceX reference. What the clauses usually cover is explained in our guide to the Launch Service Agreement (LSA).
Questions to answer from your contract, or to put to your provider in writing:
- Rebooking fee: What percentage applies, and is it calculated on the amount paid or on the full launch price?
- Credit for money paid: Is all of it credited to the new launch, as SpaceX promises for payload delays, or only part?
- Price year: Which year's price list applies to the new flight? The SpaceX booking tool lists prices per kilogram by year: $7,000 for 2026 and $7,500 for 2027 (price API, retrieved 7 November 2026). It does not list a price for later years, so a rebooking onto a later flight is a point to clarify.
- Next available flight: Is there a firm seat on a named mission, or only a promise of "a future mission"?
- Termination: Can you leave the contract after a slip, and what is refunded?
- Reflight or rollover after a partial service: Some customers ask about credits for a later flight. These are not standard published terms; if you need one, it has to be negotiated into the contract.
Step 3: Re-plan delivery and storage
A slipped launch often means the satellite is finished but has nowhere to go. Launch sites are not long-term warehouses. The SpaceX guide (section 9.5.1) says the customer delivers the payload and its ground support equipment "no more than eight weeks prior to the Launch Date unless requested by SpaceX", must ship its container and equipment away by the last scheduled integration day, and may store "no more than one standard shipping container or truck trailer at the Launch site for the duration of their integration activities." The customer also remains responsible for environmental control of the payload until it is removed from its container, "including generators and fuel."
So in most cases the satellite waits at your own facility or at a contracted storage site. What to plan for:
- Environment: Keep the satellite in the cleanliness, temperature and humidity conditions defined in your interface documents. Our guide to satellite shipping explains the container requirements.
- Batteries: Plan maintenance charging for the longer wait.
- Access if it is already integrated: NASA writes in CubeSat 101 that once a CubeSat is in its dispenser you will not have access again; after a delay of several months developers "may have an opportunity to access their CubeSats again, but this is only in extreme circumstances and is by no means guaranteed."
- Transport: Rebook freight, export documents and team travel, and check export licence validity against the new date.
Step 4: Check your radio licence
A spectrum licence can expire or default while the satellite waits on the ground. What applies depends on the licence type. For US licences, the rules are in Title 47 of the Code of Federal Regulations:
- FCC Part 25 streamlined small satellite licence (§ 25.122): The licence runs for 6 years "without the possibility of extension or replacement authorization" (§ 25.121(a)(3)). The term starts only when the licensee notifies the FCC that the first space station is in its authorised orbit and has begun operating (§ 25.121(d)(3)), so a slip does not shorten the operating term. The surety bond, however, is due within one year plus 30 days of the grant (§ 25.165(a)), regardless of the launch date.
- Other FCC Part 25 NGSO licences: The licensee must launch 50 percent of the authorised satellites and operate them within 6 years of the grant and the rest within 9 years (§ 25.164(b)). Within 15 days after a deadline, it must show compliance or tell the FCC in writing that the milestone was missed (§ 25.164(f)). A licensee that misses a milestone is in default on its bond (§ 25.165(c)).
- FCC experimental licence (Part 5): The regular term is 2 years; a renewal of up to 5 years needs "an adequate showing of need to complete the experiment" (§ 5.71(a)). A long slip can push the launch close to the end of the term.
- Amateur satellites (Part 97): The pre-space notification is due within 30 days after the launch vehicle is determined and no later than 90 days before integration into the launch vehicle (§ 97.207(g)(1)).
Our own conclusion from these rules: compare every date in your licence with the new launch date on the day you learn of the slip. If the rebooking changes the launch vehicle or moves integration, check with your licensing authority whether filings that refer to the launch need an update. Operators licensed outside the US should run the same check against their national authority's terms.
Step 5: Check your ITU deadlines
The frequency assignment behind your licence is filed with the International Telecommunication Union by your national administration. Its deadlines run independently of your launch contract. The ITU Radiocommunication Bureau sets out the rules in its World Radiocommunication Seminar material (December 2024):
- Seven-year limit: The date of bringing into use must be no later than 7 years from the date the Bureau received the advance publication information or coordination request (Radio Regulations No. 11.44). The actual date must be confirmed no later than 30 days after this deadline.
- What counts as brought into use: For non-geostationary systems in the fixed, mobile and broadcasting satellite services, a space station able to use the assignment must be deployed and maintained on one of the notified orbital planes for a continuous 90 days (No. 11.44C). For other non-geostationary systems around Earth, the deployment rule is in No. 11.44D.
- Suspension: An assignment that is already in use can be suspended for up to 3 years (No. 11.49). The Bureau must be informed no later than 6 months after the date of suspension; a late notice shortens the 3 years day by day.
- Short-duration missions (Resolution 32): The notification is submitted after launch, no later than 2 months after bringing into use, and the date of bringing into use is the date of the first launch.
- Large constellations (Resolution 35): According to the ITU, systems in the bands covered must deploy 10 percent of the constellation within two years after the end of the regulatory period for bringing into use, 50 percent within five years and the full constellation within seven years.
If a slip pushes your launch towards the seven-year limit, talk to your national administration early. It files with the ITU on your behalf.
Step 6: Check your funding cut-offs
Grants usually pay only for work done within the project period. A launch that slips past the end date can leave launch costs or operations unfunded.
- EU grants: Under the Horizon Europe model grant agreement (version 1.2, 1 June 2026), eligible costs "must be incurred in the period set out in Article 4" (Article 6.1). Changes such as a longer project duration need a formal amendment requested through the Funding and Tenders Portal (Article 39); the receiving party has 45 days to sign or object, and silence counts as rejection. The EU Amendment Guide (version 1.2, March 2026) lists the change of project duration as its own amendment type (AT25), combined with a change of Annex 1.
- ESA and EU Flight Ticket Initiative: The initiative co-funds launches on European launchers for ready-to-fly IOD/IOV satellites, selected through calls for satellites. The last listed cut-off is 15 March 2027, 18:00 CET. Details in our guide to the ESA Flight Ticket Initiative.
Our own conclusion: request the extension before the project ends, with the provider's new launch date as evidence.
Step 7: Decide whether to wait or switch
Once the dates are clear, compare the new date with the alternatives. For rideshare to sun-synchronous orbit, the SpaceX booking tool listed two open flights on 7 November 2026, with target dates in June 2027 and October 2027, both at 500 to 600 km. Integrators, small launchers and European newcomers fly on other dates. Our overview of SpaceX rideshare alternatives for 2027 and 2028 compares them.
- Wait: sensible if the new date still fits your licence, ITU and funding deadlines and the rebooking fee is lower than the cost of switching.
- Switch provider: sensible if your deadlines are tight, or if the contract lets you leave with a refund. Check that the new vehicle fits your interface, orbit and mass, and that your licences cover the change.
Worked example: a 120 kg satellite misses its rideshare
A start-up has booked a 120 kg Earth observation satellite on a SpaceX sun-synchronous rideshare at the 2027 price of $7,500 per kg. It holds an FCC streamlined small satellite licence and an EU grant. A late star tracker means the satellite cannot be delivered on time. The figures below are our own calculation from the published rules; the scenario is illustrative.
- Launch price: 120 kg at $7,500 per kg is $900,000. The 120 kg are above the 100 kg minimum of a half plate.
- Rebooking: Because the delay is on the customer's side, the published 5 to 10 percent rebooking fee applies: $45,000 to $90,000 on the launch price, with the money already paid credited to the new flight. The team asks SpaceX in writing which flight it is moved to and which year's price applies.
- Storage: The satellite stays in the team's cleanroom, with a battery charging plan, until about eight weeks before the new launch date.
- FCC licence: The 6-year term has not started, because it begins only when the satellite operates in orbit. The bond deadline of one year plus 30 days after grant is unaffected and is checked separately.
- ITU: The national administration confirms that the seven-year limit for bringing into use is still years away.
- Grant: The project end date falls before the new launch. The team requests a change of project duration through the portal immediately, with the provider's new date as evidence.
FAQ
What happens if my satellite misses its launch?
The launch usually leaves without it. NASA states that a CubeSat that is not delivered in time will not fly on that launch. Your contract then decides whether you are rebooked, at what fee, or whether you can terminate.
How much does it cost to rebook a SpaceX rideshare?
SpaceX states that if your payload is delayed, 100 percent of the money paid can be applied to a future mission, subject to a 5 to 10 percent rebooking fee. If SpaceX moves the launch because it failed to meet its own responsibilities, its user's guide says no customer rebooking fee applies.
Do I lose my FCC licence if my launch is delayed?
Not automatically. For a streamlined small satellite licence, the 6-year term starts when the satellite operates in orbit. Other Part 25 licences have launch milestones counted from the grant, and experimental licences have a fixed term, so check the dates in your grant.
How long do I have to bring an ITU frequency filing into use?
No later than 7 years from the date the ITU received the advance publication information or coordination request. Many non-geostationary systems must keep a satellite in a notified orbital plane for 90 continuous days to count as brought into use.
What if my grant ends before the new launch date?
For EU grants, costs are eligible only within the project period, and a longer duration needs a formal amendment. Request it before the project ends and attach the provider's new launch date.
Related reading
- Launch Delays: Why Satellite Launches Slip and How to Plan for Them
- Launch Service Agreement (LSA) Explained: What Is in a Satellite Launch Contract?
- SpaceX Rideshare Alternatives for 2027 and 2028
Find a new slot with one request
After a slip, time matters, and every provider has its own schedule. On Carrier Space you can see the open rideshare missions, compare launch vehicles and providers, and then send one request to up to five providers and brokers you pick. Carrier Space checks the request and forwards it anonymously, and indicative offers come back in one comparable view. Asking several providers at once raises the chance of finding a slot that fits your new date and your deadlines. In the Rideshare Marketplace, your request can also be published anonymously, with your consent, so others can join a flight. Free for customers.
Sources
- SpaceX Rideshare Payload User's Guide, Version 11, August 2026 (sections 9.2, 9.5, 9.5.1, 9.6, 9.6.1, 9.6.8)
- SpaceX Smallsat Rideshare Program (checked 7 November 2026)
- SpaceX Rideshare price configuration (API, retrieved 7 November 2026)
- SpaceX Rideshare available flights (API, retrieved 7 November 2026)
- NASA CubeSat Launch Initiative: CubeSat 101, October 2017
- eCFR, 47 CFR Part 25 (§§ 25.121, 25.122, 25.164, 25.165)
- eCFR, 47 CFR § 5.71 License period
- eCFR, 47 CFR § 97.207 Space station
- ITU Radiocommunication Bureau: Bringing into use of GSO and NGSO satellite networks, WRS-24, December 2024
- ITU Radiocommunication Bureau: Bringing into use of GSO and NGSO satellite networks, WRS-20
- ITU backgrounder: Non-geostationary satellite systems
- ESA Space Transportation: Flight Ticket Initiative
- European Commission: Horizon Europe Model Grant Agreement, version 1.2, 1 June 2026
- European Commission: EU Grants Amendment Guide, version 1.2, 15 March 2026
Cover image: Technicians remove the JPSS-1 weather satellite from its shipping container inside the Astrotech Processing Facility at Vandenberg Air Force Base, California, on 1 September 2017. Credit: NASA/Timothy Trenkle (VAFB-20170901-PH_TMT01_0034)